Module 1: Introduction and Rationale - Cpm Pert Scurve Training Module Outcomes Map

Rationale, institutional objectives, and project control workflow for the NIA Training-Workshop on PERT-CPM and S-Curve.

Open simulation
2D

Module 1: Introduction and Rationale - Cpm Pert Scurve Training Module Project Control Workflow

Rationale, institutional objectives, and project control workflow for the NIA Training-Workshop on PERT-CPM and S-Curve.

Open simulation
2D

Module 2: CPM Fundamentals and Critical Path Scheduling - Cpm Pert Scurve Training Module02 Network Builder

Network logic, activity sequencing, forward pass, backward pass, float analysis, and critical path control for construction management.

Open simulation
2D

Module 2: CPM Fundamentals and Critical Path Scheduling - Cpm Pert Scurve Training Module02 Forward Pass

Network logic, activity sequencing, forward pass, backward pass, float analysis, and critical path control for construction management.

Open simulation
2D

Module 2: CPM Fundamentals and Critical Path Scheduling - Cpm Pert Scurve Training Module02 Backward Pass

Network logic, activity sequencing, forward pass, backward pass, float analysis, and critical path control for construction management.

Open simulation
2D

Module 2: CPM Fundamentals and Critical Path Scheduling - Cpm Pert Scurve Training Module02 Float Diagnosis

Network logic, activity sequencing, forward pass, backward pass, float analysis, and critical path control for construction management.

Open simulation
2D

Module 2: CPM Fundamentals and Critical Path Scheduling - Cpm Pert Scurve Training Module02 Crashing Tradeoff

Network logic, activity sequencing, forward pass, backward pass, float analysis, and critical path control for construction management.

Open simulation
2D

Module 2: CPM Fundamentals and Critical Path Scheduling - Cpm Pert Scurve Training Module02 Diagram Visualizer

Network logic, activity sequencing, forward pass, backward pass, float analysis, and critical path control for construction management.

Open simulation
2D

Module 3: PERT Probabilistic Analysis - Cpm Pert Scurve Training Module Pert Estimator

Understand how to incorporate time uncertainty into project schedules using three-point estimating, variance, and probability analysis to support risk-informed management decisions in irrigation projects.

Open simulation
2D

Module 3: PERT Probabilistic Analysis - Cpm Pert Scurve Training Module03 Three Point Estimator

Understand how to incorporate time uncertainty into project schedules using three-point estimating, variance, and probability analysis to support risk-informed management decisions in irrigation projects.

Open simulation
2D

Module 3: PERT Probabilistic Analysis - Cpm Pert Scurve Training Module03 Variance Aggregator

Understand how to incorporate time uncertainty into project schedules using three-point estimating, variance, and probability analysis to support risk-informed management decisions in irrigation projects.

Open simulation
2D

Module 3: PERT Probabilistic Analysis - Cpm Pert Scurve Training Module03 Risk Sensitivity

Understand how to incorporate time uncertainty into project schedules using three-point estimating, variance, and probability analysis to support risk-informed management decisions in irrigation projects.

Open simulation
2D

Module 3: PERT Probabilistic Analysis - Cpm Pert Scurve Training Module03 Probability Curve

Understand how to incorporate time uncertainty into project schedules using three-point estimating, variance, and probability analysis to support risk-informed management decisions in irrigation projects.

Open simulation
2D

Module 3: PERT Probabilistic Analysis - Cpm Pert Scurve Training Module03 Contingency Decision

Understand how to incorporate time uncertainty into project schedules using three-point estimating, variance, and probability analysis to support risk-informed management decisions in irrigation projects.

Open simulation
2D

Module 3: PERT Probabilistic Analysis - Cpm Pert Scurve Training Module03 Diagram Visualizer

Understand how to incorporate time uncertainty into project schedules using three-point estimating, variance, and probability analysis to support risk-informed management decisions in irrigation projects.

Open simulation
2D

Module 4: S-Curve Monitoring and Project Control - Cpm Pert Scurve Training Module04 S Curve Envelope

Construction of planned and actual S-Curves, banana curve interpretation, progress monitoring, variance analysis, and reporting for irrigation and infrastructure projects.

Open simulation
2D

Module 4: S-Curve Monitoring and Project Control - Cpm Pert Scurve Training Module04 Progress Variance

Construction of planned and actual S-Curves, banana curve interpretation, progress monitoring, variance analysis, and reporting for irrigation and infrastructure projects.

Open simulation
2D

Module 4: S-Curve Monitoring and Project Control - Cpm Pert Scurve Training Module04 Earned Value Control

Construction of planned and actual S-Curves, banana curve interpretation, progress monitoring, variance analysis, and reporting for irrigation and infrastructure projects.

Open simulation
2D

Module 4: S-Curve Monitoring and Project Control - Cpm Pert Scurve Training Module04 Recovery Scenario

Construction of planned and actual S-Curves, banana curve interpretation, progress monitoring, variance analysis, and reporting for irrigation and infrastructure projects.

Open simulation
2D

Module 4: S-Curve Monitoring and Project Control - Cpm Pert Scurve Training Module04 Forecast Trend

Construction of planned and actual S-Curves, banana curve interpretation, progress monitoring, variance analysis, and reporting for irrigation and infrastructure projects.

Open simulation
2D

Module 4: S-Curve Monitoring and Project Control - Cpm Pert Scurve Training Module04 Diagram Visualizer

Construction of planned and actual S-Curves, banana curve interpretation, progress monitoring, variance analysis, and reporting for irrigation and infrastructure projects.

Open simulation
2D

Module 5: AI Integration and Culminating Workshop - Cpm Pert Scurve Training Module05 Diagram Visualizer

AI-assisted integration of CPM, PERT, and S-Curve outputs for schedule validation, progress assessment, reporting, and corrective action planning.

Open simulation
2D

Module 5: AI Integration and Culminating Workshop - Cpm Pert Scurve Training Module05 Workshop Scenario

AI-assisted integration of CPM, PERT, and S-Curve outputs for schedule validation, progress assessment, reporting, and corrective action planning.

Open simulation
2D

Module 5: AI Integration and Culminating Workshop - Cpm Pert Scurve Training Module05 Data Quality Gate

AI-assisted integration of CPM, PERT, and S-Curve outputs for schedule validation, progress assessment, reporting, and corrective action planning.

Open simulation
2D

Module 5: AI Integration and Culminating Workshop - Cpm Pert Scurve Training Module05 Schedule Review

AI-assisted integration of CPM, PERT, and S-Curve outputs for schedule validation, progress assessment, reporting, and corrective action planning.

Open simulation
2D

Module 5: AI Integration and Culminating Workshop - Cpm Pert Scurve Training Module05 Risk Review

AI-assisted integration of CPM, PERT, and S-Curve outputs for schedule validation, progress assessment, reporting, and corrective action planning.

Open simulation
2D

Module 5: AI Integration and Culminating Workshop - Cpm Pert Scurve Training Module05 Ai Prompt Workflow

AI-assisted integration of CPM, PERT, and S-Curve outputs for schedule validation, progress assessment, reporting, and corrective action planning.

Open simulation
2D

Guided Workshop Activities and Integrated Project Output - Complete Worked Example - Cpm Pert Scurve Training Module06 Project Control Charts

End-to-end fictional irrigation-project example with interactive CPM, PERT, S-Curve, Earned Value, activity-weight, and recovery simulations.

Open simulation