Module 3: PERT Probabilistic Analysis - Cpm Pert Scurve Training Module Pert Estimator

Understand how to incorporate time uncertainty into project schedules using three-point estimating, variance, and probability analysis to support risk-informed management decisions in irrigation projects.

Open the complete lesson

PERT Estimator Visualizer

Adjust the three-point estimates to see how they affect the expected duration and activity variance.

4 days
6 days
10 days
Expected Duration
6.33 days
te=4+4(6)+106=6.33t_e = \frac{4 + 4(6) + 10}{6} = 6.33
Variance (σ2\sigma^2)
1.00
Std Dev (σ\sigma)
1.00