Module 3: PERT Probabilistic Analysis - Cpm Pert Scurve Training Module03 Variance Aggregator

Understand how to incorporate time uncertainty into project schedules using three-point estimating, variance, and probability analysis to support risk-informed management decisions in irrigation projects.

Open the complete lesson

Project Variance & Standard Deviation Aggregator

Adjust the individual variances of activities on the critical path to see how they aggregate into the total project uncertainty.

Project Uncertainty

Project Variance (VpV_p)
Vp=1.00+0.44+0.25=1.69 days2V_p = 1.00 + 0.44 + 0.25 = 1.69 \text{ days}^2
Project Standard Deviation (σp\sigma_p)
σp=1.69=1.30 days\sigma_p = \sqrt{1.69} = 1.30 \text{ days}