Cpm Pert And S Curve Training Module2D
Module 4: S-Curve Monitoring and Project Control - Cpm Pert Scurve Training Module04 Diagram Visualizer
Construction of planned and actual S-Curves, banana curve interpretation, progress monitoring, variance analysis, and reporting for irrigation and infrastructure projects.
Open the complete lessonComprehensive S-Curve Control Diagram
Analyze Schedule Variance (SV), Cost Variance (CV), and dynamic forecasts by sliding the Data Date.
Set Reporting Data DateMonth 5
Early Stage (Month 1)Mid Stage (Month 5)Late Stage (Month 10)
SV (Month 5)-10.0%
CV (Month 5)-15.0%
Planned Value
Target accomplishment schedule based on baseline dates.
Earned Value
The budgeted value of completed physical works.
Actual Cost
Actual cash spent to achieve physical works progress.
Variances
SV (EV - PV) and CV (EV - AC) cost/schedule indicators.
Related simulations
Module 1: Introduction and Rationale - Cpm Pert Scurve Training Module Outcomes MapModule 1: Introduction and Rationale - Cpm Pert Scurve Training Module Project Control WorkflowModule 2: CPM Fundamentals and Critical Path Scheduling - Cpm Pert Scurve Training Module02 Network BuilderModule 2: CPM Fundamentals and Critical Path Scheduling - Cpm Pert Scurve Training Module02 Forward Pass