Module 4: S-Curve Monitoring and Project Control - Cpm Pert Scurve Training Module04 Diagram Visualizer

Construction of planned and actual S-Curves, banana curve interpretation, progress monitoring, variance analysis, and reporting for irrigation and infrastructure projects.

Open the complete lesson

Comprehensive S-Curve Control Diagram

Analyze Schedule Variance (SV), Cost Variance (CV), and dynamic forecasts by sliding the Data Date.

Set Reporting Data DateMonth 5
Early Stage (Month 1)Mid Stage (Month 5)Late Stage (Month 10)
SV (Month 5)-10.0%
CV (Month 5)-15.0%
Data DatePVACEVF-EVF-ACSVCV0%25%50%75%100%M0M2M4M6M8M10M12
Planned Value

Target accomplishment schedule based on baseline dates.

Earned Value

The budgeted value of completed physical works.

Actual Cost

Actual cash spent to achieve physical works progress.

Variances

SV (EV - PV) and CV (EV - AC) cost/schedule indicators.