Module 2: CPM Fundamentals and Critical Path Scheduling - Cpm Pert Scurve Training Module02 Diagram Visualizer
Network logic, activity sequencing, forward pass, backward pass, float analysis, and critical path control for construction management.
Open the complete lessonComprehensive Diagram Visualizer & Calculator
Adjust activity durations, inspect CPM forward/backward pass values, and see how float changes the project finish in real time.
Duration17d
Critical4
StatusFlexible parallel path
Activity Durations
Simulation Presets
Diagram Information
Critical Path: The active controlling route is A → B → D → E. Activities on this path have zero total float.
Selected Activity ACritical
Activity A is critical. Adding one day here directly extends the project unless another critical activity is crashed.
Activity Parameter Calculations
| ID | Activity | Duration | ES | EF | LS | LF | TF | FF | Path |
|---|---|---|---|---|---|---|---|---|---|
| A | Site Prep | 4d | 0 | 4 | 0 | 4 | 0d | 0d | Critical |
| B | Excavation | 6d | 4 | 10 | 4 | 10 | 0d | 0d | Critical |
| C | Procurement | 3d | 4 | 7 | 12 | 15 | 8d | 8d | Non-critical |
| D | Concreting | 5d | 10 | 15 | 10 | 15 | 0d | 0d | Critical |
| E | Inspection | 2d | 15 | 17 | 15 | 17 | 0d | 0d | Critical |
Related simulations
Module 1: Introduction and Rationale - Cpm Pert Scurve Training Module Outcomes MapModule 1: Introduction and Rationale - Cpm Pert Scurve Training Module Project Control WorkflowModule 2: CPM Fundamentals and Critical Path Scheduling - Cpm Pert Scurve Training Module02 Network BuilderModule 2: CPM Fundamentals and Critical Path Scheduling - Cpm Pert Scurve Training Module02 Forward Pass