Module 2: CPM Fundamentals and Critical Path Scheduling - Cpm Pert Scurve Training Module02 Diagram Visualizer

Network logic, activity sequencing, forward pass, backward pass, float analysis, and critical path control for construction management.

Open the complete lesson

Comprehensive Diagram Visualizer & Calculator

Adjust activity durations, inspect CPM forward/backward pass values, and see how float changes the project finish in real time.

Duration17d
Critical4
StatusFlexible parallel path
Activity Durations
Simulation Presets
FSFSFSFSFSA: Site Prep | Duration 4d | TF 0d | FF 0dES 0d 4EF 4ASite PrepLS 0TF 0LF 4B: Excavation | Duration 6d | TF 0d | FF 0dES 4d 6EF 10BExcavationLS 4TF 0LF 10C: Procurement | Duration 3d | TF 8d | FF 8dES 4d 3EF 7CProcurementLS 12TF 8LF 15D: Concreting | Duration 5d | TF 0d | FF 0dES 10d 5EF 15DConcretingLS 10TF 0LF 15E: Inspection | Duration 2d | TF 0d | FF 0dES 15d 2EF 17EInspectionLS 15TF 0LF 17
Diagram Information

Critical Path: The active controlling route is A → B → D → E. Activities on this path have zero total float.

Selected Activity ACritical

Activity A is critical. Adding one day here directly extends the project unless another critical activity is crashed.

Activity Parameter Calculations
IDActivityDurationESEFLSLFTFFFPath
ASite Prep4d04040d0dCritical
BExcavation6d4104100d0dCritical
CProcurement3d4712158d8dNon-critical
DConcreting5d101510150d0dCritical
EInspection2d151715170d0dCritical