Module 4: S-Curve Monitoring and Project Control - Cpm Pert Scurve Training Module04 S Curve Envelope

Construction of planned and actual S-Curves, banana curve interpretation, progress monitoring, variance analysis, and reporting for irrigation and infrastructure projects.

Open the complete lesson

S-Curve Envelope (Banana Curve)

Visualizing Early vs. Late baseline schedules and actual physical progress.

Total Project Value₱5,000,000
Severe SlippageOptimal Progress
0%25%50%75%100%M0M1M2M3M4M5M6M7M8M9M10
Early Start (Target)
Late Start (Limit)
Acceptable Envelope
Actual Accomplishment
🚨 CRITICAL DELAY (Slippage: -22.7%)Under PD 1870 and NIA rules, a negative slippage exceeding 15% is grounds for contract takeover or termination. Immediate joint-site inspection and takeover protocols are recommended.