Module 4: S-Curve Monitoring and Project Control - Cpm Pert Scurve Training Module04 Forecast Trend
Construction of planned and actual S-Curves, banana curve interpretation, progress monitoring, variance analysis, and reporting for irrigation and infrastructure projects.
Open the complete lessonEVM Forecasting & Trend Analysis
Perform trend analysis and forecast Estimate at Completion (EAC) using multiple methodologies.
EVM Variables
₱1,000,000
₱600,000
₱450,000
₱550,000
Cost Index (CPI)0.82
Schedule Index (SPI)0.75
Forecast Cost (EAC)₱1,222,222
Variance (VAC)-₱222,222
Methodology Calculations
Formula Used:
Analysis:⚠️ The project is facing a budget overrun of ₱222,222 (22.2% of BAC) under this scenario.
Choosing the right forecasting method is vital. The CPI × SPI method is a realistic indicator for projects suffering from concurrent cost and schedule creep.
Related simulations
Module 1: Introduction and Rationale - Cpm Pert Scurve Training Module Outcomes MapModule 1: Introduction and Rationale - Cpm Pert Scurve Training Module Project Control WorkflowModule 2: CPM Fundamentals and Critical Path Scheduling - Cpm Pert Scurve Training Module02 Network BuilderModule 2: CPM Fundamentals and Critical Path Scheduling - Cpm Pert Scurve Training Module02 Forward Pass