Guided Workshop Activities and Integrated Project Output - Complete Worked Example - Cpm Pert Scurve Training Module06 Project Control Charts

End-to-end fictional irrigation-project example with interactive CPM, PERT, S-Curve, Earned Value, activity-weight, and recovery simulations.

Open the complete lesson

Module 6 simulated graph

Early, Late, and Actual S-Curve Envelope

Inspect the planned envelope, reporting-period variance, and first boundary breach.

Fictional training data
S-Curve envelope and actual progress for the fictional canal project0%20%40%60%80%100%W0W1W2W3W4W5W6W7W8First boundary breach: W6Early startLate startActual

Early plan

90.0%

Late plan

89.4%

Actual

76.0%

Variance

-14.0 / -13.4 pts

Simulation only. Read the graph together with the controlled tables, assumptions, source records, and quality-gate findings.