Project Control and Monitoring - Theory & Concepts
Tracking project progress using Earned Value Management and S-Curves.
Open the complete lessonEarned Value Management (EVM) Simulator
Adjust the Planned Value, Earned Value, and Actual Cost to analyze project performance indices ( and ).
Key:
- : Estimated value of planned work
- : Estimated value of completed work
- : Actual cost incurred
Schedule Perf. Index ()
0.90
Behind Schedule
Cost Perf. Index ()
0.82
Over Budget
Schedule Variance ()-$10,000
Cost Variance ()-$20,000
Value Comparison
$100,000
$90,000
$110,000