Project Planning and Scheduling - Theory & Concepts

Time management using CPM, PERT, and resource leveling techniques.

Open the complete lesson

Dynamic Scheduling Overview

Modify durations to observe how dependencies propagate early and late times through the network.

5 d
10 d
8 d
6 d

Quick Reference

Forward Pass:max(EF_pred)
Backward Pass:min(LS_succ)
Total Float:LS - ES
Project Duration21 Days
Critical PathA → B → D
CPM Network DiagramNode A: Duration 5, Float 00A5055TF: 0 Node B: Duration 10, Float 05B1551015TF: 0 Node C: Duration 8, Float 25C137815TF: 2 Node D: Duration 6, Float 015D2115621TF: 0
Non-Critical
Critical Path