Cost Estimating - Theory & Concepts

Methodologies for cost estimation, quantity takeoff, and unit price analysis.

Open the complete lesson

Cost Estimator & Breakdown

Calculate total direct and indirect costs by adjusting labor, materials, equipment, and overhead.

Calculation Formulas

Cdirect=Clabor+Cmat+CequipC_{\text{direct}} = C_{\text{labor}} + C_{\text{mat}} + C_{\text{equip}}
Coverhead=Cdirect×(O%100)C_{\text{overhead}} = C_{\text{direct}} \times \left( \frac{O_{\%}}{100} \right)
Ctotal=Cdirect+CoverheadC_{\text{total}} = C_{\text{direct}} + C_{\text{overhead}}
Total Direct Cost$180,000
Overhead & Profit (15%)$27,000
Total Estimated Cost$207,000

Cost Breakdown Proportion

Labor
Materials
Equipment
Overhead