Project Control and Monitoring - Theory & Concepts - Construction Methods And Project Management Progress Measurement Trainer

Tracking project progress using Earned Value Management and S-Curves.

Open the complete lesson

Progress Measurement Trainer

Explore objective methods for calculating Earned Value (EV) by measuring physical progress. Avoid subjective "percent complete" estimates.

Repetitive Task: Laying 1,000 Bricks

Most objective method. EV is directly proportional to physical pieces installed.

Bricks Laid: 250Total: 1000

Earned Value Calculation

Task Budget (BAC\text{BAC})
$50,000
×\times
Objective Progress
25%
==
Earned Value (EV\text{EV})
$12,500