Back to Construction Methods And Project Management repository
Construction Methods And Project Management2D

Project Control and Monitoring - Theory & Concepts - Construction Methods And Project Management Evm Forecast Trainer

Tracking project progress using Earned Value Management and S-Curves.

Open the complete lesson

EVM Forecasting Trainer

Adjust the current Earned Value metrics to see how they mathematically forecast the final project cost (EAC) and required future efficiency (TCPI).

SPI\text{SPI}
0.80
Behind Schedule
CPI\text{CPI}
0.89
Over Budget

Forecasting Results

Estimate at Completion (EAC\text{EAC})$1,125,000
EAC=BACCPI\text{EAC} = \frac{\text{BAC}}{\text{CPI}}
Estimate to Complete (ETC\text{ETC})$675,000
ETC=EACAC\text{ETC} = \text{EAC} - \text{AC}
Variance at Completion (VAC\text{VAC})-$125,000
VAC=BACEAC\text{VAC} = \text{BAC} - \text{EAC}
To-Complete Perf. Index (TCPI\text{TCPI})1.091
TCPI=BACEVBACAC\text{TCPI} = \frac{\text{BAC} - \text{EV}}{\text{BAC} - \text{AC}}
* Efficiency needed on remaining work to hit original BAC. High value means achieving BAC is unlikely.