Project Control and Monitoring
Sample Problem: EVM Analysis - Basic Calculation
Problem Statement: At month 6, a project has a Planned Value (PV) or Budgeted Cost of Work Scheduled (BCWS) of $500,000. The Earned Value (EV) or Budgeted Cost of Work Performed (BCWP) is $450,000. The Actual Cost (AC) or Actual Cost of Work Performed (ACWP) is $480,000. Calculate CV, SV, CPI, and SPI.
Step-by-Step Solution
0 of 5 Steps CompletedSample Problem: Forecasting Estimate at Completion (EAC)
Problem Statement: Using the data from the previous problem (PV = \500,000EV = $450,000AC = $480,000CPI = 0.9375), if the original Budget at Completion (BAC) is \1,000,000, what is the new Estimate at Completion (EAC) assuming the current cost performance will continue for the rest of the project?
Step-by-Step Solution
0 of 5 Steps CompletedSample Problem: Forecasting EAC - Atypical Variances
Problem Statement: A project has a BAC of $2,000,000. At the halfway point, AC = \1,100,000EV = $1,000,000. The project manager realizes the \100k overrun was caused by a singular, unrepeatable event (a freak storm that damaged materials). The rest of the work will proceed at the originally budgeted rate. Calculate the new EAC.
Step-by-Step Solution
0 of 3 Steps CompletedSample Problem: To-Complete Performance Index (TCPI)
Problem Statement: A project has a BAC = \5,000,000EV = $2,000,000AC = $2,500,000. The owner refuses to increase the budget, so the project must finish within the original \5M BAC. What cost efficiency (TCPI) must the contractor maintain for the remainder of the work to hit this target?
Step-by-Step Solution
0 of 3 Steps CompletedSample Problem: Schedule Duration Forecasting
Problem Statement: A construction project was scheduled to be completed in 12 months. At the end of month 4, the project has a of . If the current schedule efficiency is maintained, what is the new Estimated Duration (ED)?
Step-by-Step Solution
0 of 3 Steps CompletedSample Problem: Cost and Schedule Variances as Percentages
Problem Statement: For a bridge project, the current values are EV = \1,200,000PV = $1,500,000AC = $1,350,000CV%SV%$) to determine the relative magnitude of the deviations.
Step-by-Step Solution
0 of 5 Steps CompletedSample Problem: EAC with Combined Schedule and Cost Impact
Problem Statement: A project has a BAC = \4,000,000EV = $1,500,000AC = $1,800,000PV = $1,700,000EACCPISPI$.
Step-by-Step Solution
0 of 5 Steps CompletedSample Problem: Re-estimating ETC (Bottom-Up Forecast)
Problem Statement: A project with a BAC = \8,000,000EV = $4,000,000AC = $5,200,000. The initial assumptions were fundamentally flawed, and past performance is not a reliable indicator for future work. Management decides to perform a bottom-up estimate for the remaining work, which is calculated to be \4,500,000. Calculate the new EAC and VAC.
Step-by-Step Solution
0 of 4 Steps CompletedSample Problem: TCPI to achieve revised EAC
Problem Statement: Using the data from the previous problem (BAC = \8,000,000EV = $4,000,000AC = $5,200,000EAC = $9,700,000TCPI) required to meet the new management-approved EAC of \9,700,000.
Step-by-Step Solution
0 of 3 Steps CompletedSample Problem: Evaluating Progress using Units Completed
Problem Statement: A contractor is pouring a 5,000 square foot concrete slab. The total budgeted cost for this task is $25,000. At the end of the first day, the contractor has successfully poured 1,250 square feet. Using the units completed method, calculate the Earned Value (EV).
Step-by-Step Solution
0 of 3 Steps CompletedSample Problem: Evaluating Progress using Incremental Milestones
Problem Statement: A task involves fabricating and installing a specialized steel truss with a total budget of $120,000. The progress is tied to three milestones:
- Milestone 1: Fabrication complete (40%)
- Milestone 2: Delivery to site (20%)
- Milestone 3: Final installation (40%)
Currently, the truss is fabricated and delivered, but not yet installed. Calculate the Earned Value.
Step-by-Step Solution
0 of 4 Steps CompletedSample Problem: Forecasting Future Value Based on S-Curve Schedule Variance
Problem Statement: At month 4 of a 10-month project, the Planned Value (PV) on the baseline S-Curve was expected to be 450,000 and the Earned Value (EV) is only $300,000. What is the Schedule Variance (SV) and Cost Variance (CV), and what do these signify regarding the shape of the current S-Curves relative to the baseline?