CPM Fundamentals - Worked Examples

CPM, Pert, and S-Curve Training Module

Example 1: Determining Early Finish for Single Activity

A canal excavation activity has an Early Start (ESES) of day 4.004.00 and a duration of 6.006.00 days. Calculate the Early Finish (EFEF) of the excavation.

Step-by-Step Solution

0 of 2 Steps Completed
1

Example 12: Network Diagram Logic for Curing and Testing Constraints

A canal turnover sequence requires the following dependent activities:

  • Activity F (Concrete Lining) finishes on day 30.030.0.
  • Activity G (Concrete Curing) requires 14.014.0 days and must finish before any testing can occur. It depends directly on Activity F.
  • Activity H (Water Delivery Testing) requires 5.005.00 days and depends directly on Activity G.
  • Activity I (Final Turnover Inspection) depends on Activity H and requires 2.002.00 days.

Calculate the Early Finish (EFEF) of the Final Turnover Inspection.

Step-by-Step Solution

0 of 3 Steps Completed
1

Example 4: Predecessor Logic with Access Constraints

A lateral canal excavation (Activity C) requires Right-of-Way (ROW) clearing (Activity A) to be finished. The clearing finishes on day 12.012.0. However, due to local community access constraints, the equipment cannot mobilize to the site until day 15.015.0 (Activity B). If Activity C requires both Activity A and Activity B to be completed before it can start, calculate the Early Start of the lateral canal excavation.

Step-by-Step Solution

0 of 3 Steps Completed
1

Example 2: Activity Duration Estimation for Canal Excavation

A 500 m500 \text{ m} canal section requires 2500 m32500 \text{ m}^3 of excavation. A backhoe and dump truck crew has a verified daily output of 250 m3/day250 \text{ m}^3\text{/day}. Calculate the planned duration for the canal excavation activity, assuming a 0.800.80 efficiency factor due to limited site access.

Step-by-Step Solution

0 of 2 Steps Completed
1

Example 3: Early Start with Multiple Predecessors

Concrete lining can begin only after canal excavation, subgrade preparation, and formwork are completely finished. Their Early Finishes are day 8.008.00, day 10.010.0, and day 9.009.00, respectively. Calculate the Early Start for the concrete lining activity.

Step-by-Step Solution

0 of 2 Steps Completed
1

Example 5: Computing Total Float for an Irrigation Structure

A structure installation activity has an Early Start (ESES) of day 12.012.0, Early Finish (EFEF) of day 17.017.0, Late Start (LSLS) of day 15.015.0, and Late Finish (LFLF) of day 20.020.0. Calculate the Total Float.

Step-by-Step Solution

0 of 2 Steps Completed
1

Example 6: Identifying the Critical Path in a Simplified Network

A simplified irrigation project network has three continuous paths from start to finish:

  • Path A: Site Survey, Canal Excavation, Concreting, Concrete Curing = 18.018.0 days
  • Path B: Site Survey, Material Delivery, Structure Installation = 14.014.0 days
  • Path C: Site Survey, Final Inspection, Project Turnover = 12.012.0 days

Identify the critical path and determine the minimum project completion time.

Step-by-Step Solution

0 of 2 Steps Completed
1

Example 7: Free Float for a Material Delivery Activity

A material delivery activity finishes on day 7.007.00 (EF=7.00EF = 7.00). Its immediate and only successor, structure installation, has an Early Start (ESES) of day 11.011.0. Calculate the free float of the delivery activity.

Step-by-Step Solution

0 of 2 Steps Completed
1

Example 8: Early Start and Early Finish in a Network Sequence

An activity sequence consists of Canal Excavation (Task A) followed by Subgrade Preparation (Task B). Task A has an Early Start (ESES) of 00 and a duration of 6.006.00 days. Task B has a duration of 4.004.00 days. Calculate the Early Start and Early Finish for both tasks.

Step-by-Step Solution

0 of 3 Steps Completed
1

Example 9: Backward Pass Scheduling for Curing

Concrete Curing (Task C) has a duration of 5.005.00 days and precedes Water Delivery Testing (Task D), which has a Late Start (LSLS) of 12.012.0 days. If Task D is the only immediate successor of Task C, calculate the Late Finish (LFLF) and Late Start (LSLS) of Task C.

Step-by-Step Solution

0 of 3 Steps Completed
1

Example 10: Total Float and Free Float for Procurement

Procurement of steel gates (Activity E) has a duration of 8.008.00 days, with ES=4.00ES = 4.00 days and LS=6.00LS = 6.00 days. Its immediate successors are Gate Installation (Activity F, which has ES=15.0ES = 15.0 days) and Electrical Wiring (Activity G, which has ES=16.0ES = 16.0 days). Calculate the Total Float and Free Float of Activity E.

Step-by-Step Solution

0 of 4 Steps Completed
1

Example 11: Determining Critical Path in Complex Irrigation Works

A project network diagram for an irrigation dam has three parallel paths with expected durations:

  • Path 1: Cofferdam Construction \rightarrow River Diversion \rightarrow Core Trench Excavation with duration 18.518.5 days
  • Path 2: Foundation Grouting \rightarrow Embankment Fill \rightarrow Spillway Concreting with duration 22.022.0 days
  • Path 3: Access Road Grading \rightarrow Temporary Facilities Setup with duration 15.015.0 days

Identify the critical path and the total project duration.

Step-by-Step Solution

0 of 2 Steps Completed
1