CPM Fundamentals - Worked Examples
CPM, Pert, and S-Curve Training Module
Example 1: Determining Early Finish for Single Activity
A canal excavation activity has an Early Start () of day and a duration of days. Calculate the Early Finish () of the excavation.
Step-by-Step Solution
0 of 2 Steps CompletedExample 12: Network Diagram Logic for Curing and Testing Constraints
A canal turnover sequence requires the following dependent activities:
- Activity F (Concrete Lining) finishes on day .
- Activity G (Concrete Curing) requires days and must finish before any testing can occur. It depends directly on Activity F.
- Activity H (Water Delivery Testing) requires days and depends directly on Activity G.
- Activity I (Final Turnover Inspection) depends on Activity H and requires days.
Calculate the Early Finish () of the Final Turnover Inspection.
Step-by-Step Solution
0 of 3 Steps CompletedExample 4: Predecessor Logic with Access Constraints
A lateral canal excavation (Activity C) requires Right-of-Way (ROW) clearing (Activity A) to be finished. The clearing finishes on day . However, due to local community access constraints, the equipment cannot mobilize to the site until day (Activity B). If Activity C requires both Activity A and Activity B to be completed before it can start, calculate the Early Start of the lateral canal excavation.
Step-by-Step Solution
0 of 3 Steps CompletedExample 2: Activity Duration Estimation for Canal Excavation
A canal section requires of excavation. A backhoe and dump truck crew has a verified daily output of . Calculate the planned duration for the canal excavation activity, assuming a efficiency factor due to limited site access.
Step-by-Step Solution
0 of 2 Steps CompletedExample 3: Early Start with Multiple Predecessors
Concrete lining can begin only after canal excavation, subgrade preparation, and formwork are completely finished. Their Early Finishes are day , day , and day , respectively. Calculate the Early Start for the concrete lining activity.
Step-by-Step Solution
0 of 2 Steps CompletedExample 5: Computing Total Float for an Irrigation Structure
A structure installation activity has an Early Start () of day , Early Finish () of day , Late Start () of day , and Late Finish () of day . Calculate the Total Float.
Step-by-Step Solution
0 of 2 Steps CompletedExample 6: Identifying the Critical Path in a Simplified Network
A simplified irrigation project network has three continuous paths from start to finish:
- Path A: Site Survey, Canal Excavation, Concreting, Concrete Curing = days
- Path B: Site Survey, Material Delivery, Structure Installation = days
- Path C: Site Survey, Final Inspection, Project Turnover = days
Identify the critical path and determine the minimum project completion time.
Step-by-Step Solution
0 of 2 Steps CompletedExample 7: Free Float for a Material Delivery Activity
A material delivery activity finishes on day (). Its immediate and only successor, structure installation, has an Early Start () of day . Calculate the free float of the delivery activity.
Step-by-Step Solution
0 of 2 Steps CompletedExample 8: Early Start and Early Finish in a Network Sequence
An activity sequence consists of Canal Excavation (Task A) followed by Subgrade Preparation (Task B). Task A has an Early Start () of and a duration of days. Task B has a duration of days. Calculate the Early Start and Early Finish for both tasks.
Step-by-Step Solution
0 of 3 Steps CompletedExample 9: Backward Pass Scheduling for Curing
Concrete Curing (Task C) has a duration of days and precedes Water Delivery Testing (Task D), which has a Late Start () of days. If Task D is the only immediate successor of Task C, calculate the Late Finish () and Late Start () of Task C.
Step-by-Step Solution
0 of 3 Steps CompletedExample 10: Total Float and Free Float for Procurement
Procurement of steel gates (Activity E) has a duration of days, with days and days. Its immediate successors are Gate Installation (Activity F, which has days) and Electrical Wiring (Activity G, which has days). Assume one calendar, finish-to-start zero-lag relationships, and consistent backward-pass data without an earlier imposed deadline. Calculate the Total Float and Free Float of Activity E.
Step-by-Step Solution
0 of 4 Steps CompletedExample 11: Determining Critical Path in Complex Irrigation Works
A project network diagram for an irrigation dam has three parallel paths with expected durations:
- Path 1: Cofferdam Construction River Diversion Core Trench Excavation with duration days
- Path 2: Foundation Grouting Embankment Fill Spillway Concreting with duration days
- Path 3: Access Road Grading Temporary Facilities Setup with duration days
Identify the critical path and the total project duration.