Earthwork Profiling
Learning Objectives
- Understand the purpose and methods of earthwork profiling and cross-sectioning.
- Learn how to compute cross-sectional areas and earthwork volumes using standard methods.
- Analyze mass haul diagrams to determine optimal material movement and economics.
Overview
Earthwork involves the excavation (cut) and placing (fill or embankment) of soil and rock to create a finished grade for a civil engineering project, such as a highway, railway, or canal. Profiling and cross-sectioning are the fundamental surveying techniques used to quantify these volumes, which are critical for cost estimation, contractor payment, and resource planning.
Cross-Sections
Definition
A cross-section is a profile of the ground surface taken at right angles to the longitudinal centerline of the route. By combining the natural ground profile with the proposed design template (the shape of the finished roadbed, including lanes, shoulders, and side slopes), the area of cut or fill at any specific station can be determined.
Types of Cross-Sections
- Level Section: The ground surface is horizontal transversely. Only the centerline cut/fill depth is needed to compute the area.
- Three-Level Section: The ground slopes uniformly from the centerline to both side stakes. It is defined by three points: the centerline depth and the horizontal/vertical coordinates of the two slope stakes.
- Five-Level Section: Used when the ground is highly irregular, requiring intermediate elevation shots between the centerline and the slope stakes.
- Side-Hill Section: A cross-section where the proposed grade line intersects the natural ground slope, resulting in excavation (cut) on one side of the centerline and embankment (fill) on the other.
Area Computation Methods
Once the coordinates (offsets from centerline and elevations relative to grade) of a cross-section are known, the area can be calculated. The most common method used in route surveying is the Coordinate Method (Shoelace Formula).
For a cross-section defined by vertices ordered consecutively around the perimeter:
Coordinate Method (Shoelace Formula)
Calculates the area of a cross-section based on its vertices.
Variables
| Symbol | Description | Unit |
|---|---|---|
| Horizontal distance (offset) from the centerline | - | |
| Vertical distance from the base grade | - |
Volume Computation
Volume Computation Overview
The volume of earthwork is calculated between successive cross-sections along the route.
1. Average End Area Method
The Average End Area method is the most widely used technique for earthwork volume calculations due to its simplicity. It assumes that the volume between two cross-sections is exactly the average of their two areas multiplied by the distance between them.
Average End Area Method
Computes the volume between two cross-sections by averaging their areas.
Variables
| Symbol | Description | Unit |
|---|---|---|
| Volume of cut or fill | - | |
| Cross-sectional area at station 1 | - | |
| Cross-sectional area at station 2 | - | |
| Horizontal distance between the stations | - |
Average End Area Limitation
The Average End Area method tends to overestimate the true volume, especially when and differ significantly. However, it is generally accepted by transportation agencies and forms the basis of most contractual payments.
2. Prismoidal Formula
When higher accuracy is required, or when the ground is highly irregular causing significant differences between adjacent areas, the Prismoidal formula is used. A prismoid is a solid whose ends are parallel polygons and whose sides are quadrilaterals or triangles.
Prismoidal Formula
Computes the exact prismoidal volume for irregular grounds.
Variables
| Symbol | Description | Unit |
|---|---|---|
| Prismoidal volume | - | |
| Cross-sectional area at station 1 | - | |
| Cross-sectional area at station 2 | - | |
| Area of a cross-section located exactly midway between A_1 and A_2 | - | |
| Distance between cross-sections | - |
3. Prismoidal Correction
Rather than computing directly, it is often easier to compute the volume using the Average End Area method and then apply a Prismoidal Correction () to obtain the exact prismoidal volume.
Prismoidal Volume with Correction
Adjusts the Average End Area volume by subtracting the Prismoidal Correction.
Variables
| Symbol | Description | Unit |
|---|---|---|
| Exact prismoidal volume | - | |
| Volume computed by the Average End Area method | - | |
| Prismoidal Correction | - |
Standard Three-Level Section Correction
For a standard three-level section, the correction formula is:
Prismoidal Correction for Three-Level Section
Computes the correction based on widths and heights.
Variables
| Symbol | Description | Unit |
|---|---|---|
| Prismoidal Correction | - | |
| Distance between cross-sections | - | |
| Total top width of cross-section 1 | - | |
| Total top width of cross-section 2 | - | |
| Centerline height of cross-section 1 | - | |
| Centerline height of cross-section 2 | - |
4. Simpson's 1/3 Rule for Volumes
When there is an odd number of cross-sections (meaning an even number of intervals) spaced at a constant distance , Simpson's 1/3 rule can be applied to calculate the total volume. It generally yields a more accurate result than applying the average end area method repeatedly, as it inherently approximates the prismoidal volume over parabolic profiles.
Simpson's 1/3 Rule for Volumes
Approximates the prismoidal volume over parabolic profiles for an odd number of cross-sections.
Variables
| Symbol | Description | Unit |
|---|---|---|
| Total volume | - | |
| Constant distance between consecutive cross-sections | - | |
| Area of the first cross-section | - | |
| Area of the last cross-section | - | |
| Sum of the areas of the even-numbered cross-sections | - | |
| Sum of the areas of the remaining odd-numbered cross-sections | - |
Shrinkage and Swell
Material Volume Changes
Earthwork materials change volume during excavation and compaction. This must be accounted for when balancing cut and fill volumes.
- Swell: When rock or dense soil is excavated, it breaks up and increases in volume.
- Shrinkage: When loose excavated material is placed in a fill and mechanically compacted, it usually occupies less volume than it did in its original natural state.
To equate cut and fill volumes, a Shrinkage Factor or Swell Factor is applied, usually to the fill volume, to determine the equivalent volume of required excavation (bank measure).
Mass Haul Diagram
Definition
A mass haul diagram (or simply mass diagram) is a continuous curve showing the accumulated algebraic sum of earthwork volume (cut being positive, fill being negative) from an initial station to any succeeding station along the route profile.
It is a powerful graphical tool used by engineers and contractors to plan the movement of excavated material, determine haul distances, and select equipment.
Properties of the Mass Diagram
- Rising and Falling: The curve rises where there is an excess of excavation (cut) and falls where there is a deficiency (fill).
- Peaks and Valleys: A peak occurs where a cut transitions into a fill (grade line is above the ground line). A valley (lowest point) occurs where a fill transitions into a cut.
- Balance Lines: Any horizontal line drawn to intersect the mass curve at two points indicates a balance between cut and fill between those two stations. The material excavated between those stations exactly equals the material required for fill.
- Area under the Curve: The area between the mass curve and a balance line represents the haul (volume distance) required to move the balanced material.
Freehaul and Overhaul
- Freehaul: The maximum distance earth can be moved without extra compensation to the contractor. It is considered part of the basic excavation cost. The freehaul volume is calculated from the balance points on the mass diagram separated by the freehaul distance ().
- Overhaul (): If material must be moved further than the freehaul distance to balance the cut and fill, the extra distance is termed "overhaul." The contractor is paid a premium for overhaul, usually calculated in units of station-meters.
Overhaul Calculation
Computes the required overhaul volume.
Variables
| Symbol | Description | Unit |
|---|---|---|
| Overhaul | - | |
| Amount of material moved beyond the freehaul distance | - | |
| Average distance the material is hauled | - | |
| Freehaul distance | - |
Borrow and Waste
When a project is not perfectly balanced (the mass diagram ends above or below zero):
- Borrow: Material obtained from outside the project limits when there is a deficiency of cut (excess fill).
- Waste: Excavated material that cannot be used on the project (excess cut) and must be disposed of elsewhere.
The choice to overhaul existing material versus wasting it and borrowing new material depends entirely on the relative cost.
Limit of Economic Haul (LEH)
The Limit of Economic Haul is the distance at which the cost of overhauling excavated material equals the cost of obtaining borrow material from nearby pits. If the required haul distance exceeds the LEH, it is cheaper to waste the cut and borrow new material for the fill.
Limit of Economic Haul (LEH)
Calculates the break-even haul distance for overhaul vs. borrow.
Variables
| Symbol | Description | Unit |
|---|---|---|
| Limit of Economic Haul | - | |
| Distance material can be moved free of extra cost | - | |
| Cost of excavating from a borrow pit | - | |
| Cost per unit volume-distance for overhaul | - |
- Earthwork profiling involves cross-sectioning (level, 3-level, side-hill) to determine the area of cut and fill.
- The Coordinate Method (Shoelace Formula) is commonly used to calculate cross-sectional areas.
- The Average End Area method () is standard for volume computation, though it slightly overestimates.
- The Prismoidal formula provides exact volumes; alternatively, a Prismoidal Correction can be subtracted from the Average End Area volume.
- Shrinkage and swell factors must be applied because soil changes volume when excavated and compacted.
- A Mass Haul Diagram visually tracks accumulated earthwork volume, helping planners balance cut/fill, determine haul distances, calculate overhaul costs, and identify the need for borrow or waste based on the Limit of Economic Haul.