Earthworks Examples and Applications
The following examples demonstrate calculations for soil volume conversion, trucking requirements, mass haul balancing, safe excavation slopes, equipment productivity, earthwork volume calculation methods, and conceptual earthwork principles.
Volume Conversion: Bank to Compacted (Shrinkage Factor)
A project requires of compacted fill (embankment). The soil has a shrinkage factor of (from Bank to Compacted). How many Bank cubic meters must be excavated?
Step-by-Step Solution
0 of 2 Steps CompletedVolume Conversion: Haul Volume (Swell Factor)
Using the bank volume calculated previously (), determine the loose volume that must be hauled if the soil has a swell of .
Step-by-Step Solution
0 of 2 Steps CompletedNumber of Truck Loads
Using the previous example where must be hauled, if each dump truck carries (loose volume), how many truck trips are required?
Step-by-Step Solution
0 of 3 Steps CompletedMass Haul Diagram Calculation
A highway section has a cut volume of (Bank Cubic Meters) and a fill requirement of (Compacted Cubic Meters). The soil has a shrinkage factor of . Calculate the net balance of earthwork. Do we need to borrow soil or waste soil?
Step-by-Step Solution
0 of 4 Steps CompletedSafe Slopes (Angle of Repose)
An excavation must reach a depth of in dry sand. The angle of repose for dry sand is . What is the minimum required horizontal setback from the top edge of the excavation to ensure the side slopes do not collapse (assuming no shoring is used)?
Step-by-Step Solution
0 of 4 Steps CompletedSoil Compaction: Dry Density Calculation
A soil sample has a wet density of and a moisture content of . Calculate the dry density of the soil.
Step-by-Step Solution
0 of 4 Steps CompletedEarthwork Volume by Average End Area Method
A section of a proposed road has a cut area of at station and a cut area of at station . Calculate the volume of earth to be excavated using the average end area method.
Step-by-Step Solution
0 of 4 Steps CompletedEarthwork Volume by Prismoidal Formula
For a more accurate calculation of a road section, the areas at the start, middle, and end are evaluated. The cut area at is , at (middle) is , and at is . Calculate the volume using the Prismoidal Formula.
Step-by-Step Solution
0 of 4 Steps CompletedExcavator Productivity Calculation
An excavator has a bucket capacity of . The fill factor for the soil is . The cycle time for the excavator is , and it operates for per hour (efficiency factor of ). Calculate the hourly production rate in loose cubic meters per hour.
Step-by-Step Solution
0 of 4 Steps CompletedEquipment Fleet Matching: Excavators vs Trucks
An excavator produces . Dump trucks being used each have a capacity of and an average round-trip travel time of . Assuming an efficiency of for the trucks, determine the number of trucks required to keep the excavator operating continuously.
Step-by-Step Solution
0 of 4 Steps CompletedConceptual Case Study: Soil Swell and Logistics
A contractor is excavating a large basement in a tight urban environment. The original design estimated the required excavation at of dense clay. However, the project manager failed to account for the soil's swell factor when ordering trucks. What are the logistical consequences of this oversight?
Step-by-Step Solution
0 of 3 Steps CompletedConceptual Case Study: Mass Haul and Borrow Pits
A 10-kilometer highway project has rolling terrain. The mass haul diagram shows a large deficit of fill material in the first 5 kilometers and a massive surplus of cut material in the last 5 kilometers. The contractor considers hauling the surplus from km 5-10 to fill the deficit at km 0-5. What factors must be evaluated before proceeding with this plan?
Step-by-Step Solution
0 of 3 Steps CompletedConceptual Case Study: Excavation Safety and Shoring
A utility trench needs to be excavated to a depth of to install a new sewer line. The site is located in an existing roadway with adjacent buildings and active traffic lanes. The soil is a mix of loose sand and gravel. Why is sloping or benching not a viable option for this excavation, and what must be done instead?
Step-by-Step Solution
0 of 3 Steps CompletedConceptual Case Study: Compaction and Moisture Content
During the construction of an earthen dam, the quality control inspector notes that the contractor is struggling to reach the required of standard Proctor maximum dry density. The soil being compacted is a clayey silt. The contractor is using heavy sheepsfoot rollers and making numerous passes, but the density is not improving. What is the most likely cause, and how should it be resolved?