Project Planning and Scheduling Examples
PERT Expected Time Calculation
Problem Statement: An activity has the following time estimates: Optimistic () = 4 days, Most Likely () = 7 days, and Pessimistic () = 16 days. Calculate the expected duration () and the variance () of the activity.
Step-by-Step Solution
0 of 3 Steps CompletedPERT Probability of Completion
Problem Statement: A project has an expected critical path length () of 40 days and a project standard deviation () of 2 days. What is the probability that the project will be completed in 43 days or less?
Step-by-Step Solution
0 of 4 Steps CompletedCritical Path and Total Float
Problem Statement: Activity D has an Early Start () of day 10, a duration () of 5 days, a Late Finish () of day 20. Calculate the Early Finish (), Late Start (), Total Float (), and Free Float () if its only successor, Activity E, has an of day 17.
Step-by-Step Solution
0 of 5 Steps CompletedSchedule Crashing (Cost Slope)
Problem Statement: An activity normally takes 10 days and costs $5,000. It can be "crashed" (expedited) to 7 days at a total cost of $6,500. Calculate the cost slope. If the project manager needs to save 2 days on the critical path, how much extra will it cost?
Step-by-Step Solution
0 of 4 Steps CompletedForward Pass Calculation
Problem Statement: A project begins with Activity A (duration = 4 days) and Activity B (duration = 6 days). Both start on day 0. Activity C (duration = 5 days) depends on Activity A. Activity D (duration = 3 days) depends on both A and B. Calculate the Early Start () and Early Finish () for all four activities.
Step-by-Step Solution
0 of 4 Steps CompletedBackward Pass Calculation
Problem Statement: Continuing from the previous example, the project ends after Activities C and D are completed. The required project duration is 9 days. Calculate the Late Finish () and Late Start () for all four activities.
Step-by-Step Solution
0 of 4 Steps CompletedPERT Expected Project Duration and Variance
Problem Statement: A project consists of three activities on its critical path: Activity X, Activity Y, and Activity Z. Their expected durations () are 5, 8, and 12 days, respectively. Their variances () are 1.5, 2.0, and 3.5. Calculate the expected project duration () and project standard deviation ().
Step-by-Step Solution
0 of 4 Steps CompletedAdvanced Schedule Crashing with Parallel Paths
Problem Statement: A project has two parallel critical paths, Path 1 and Path 2, both with a current duration of 20 days. To reduce the project duration to 19 days, you must crash activities on both paths simultaneously. On Path 1, Activity M can be crashed for $400/day. On Path 2, Activity N can be crashed for $300/day, and Activity P can be crashed for $500/day. Additionally, there is a common Activity Q that lies on both paths and can be crashed for $800/day. What is the most cost-effective way to save 1 day on the project schedule?