Testing Standards and Quality Assurance — Worked Examples
These examples follow the traceability chain from lot and sample through measurement, reporting, and engineering disposition. Test methods define how measurements are made; specifications and codes define acceptance.
Example 1 — Lot, sample, and specimen traceability
A concrete report identifies two cylinders as C-104A and C-104B but does not identify the truck, placement location, sample time, or batch represented. Determine why the report is incomplete for acceptance use.
Step-by-Step Solution
0 of 3 Steps CompletedExample 2 — Mean, sample standard deviation, and coefficient of variation
Five replicate test results are 30.1, 29.8, 30.4, 30.0, and 29.9 MPa. Calculate the mean, sample standard deviation, and coefficient of variation.
Step-by-Step Solution
0 of 3 Steps CompletedExample 3 — Precise but biased measurement system
A certified reference value is . A laboratory reports 480.1, 480.5, 479.8, 480.2, and 480.0 MPa. Interpret precision and bias qualitatively.
Step-by-Step Solution
0 of 3 Steps CompletedExample 4 — Calibration versus verification
A compression machine received formal calibration six months ago. Before today's test, a required verification check falls outside the permitted tolerance. The annual calibration due date has not passed. Decide whether testing should continue.
Step-by-Step Solution
0 of 3 Steps CompletedExample 5 — Significant figures and reporting precision
A calculation produces , but the governing test method requires reporting strength to the nearest . Determine the reportable value.
Step-by-Step Solution
0 of 2 Steps CompletedExample 6 — Valid failing result versus invalid test
A material result falls below the project limit. The technician proposes deleting it because a second test on another specimen passes. Determine the correct quality process.
Step-by-Step Solution
0 of 3 Steps CompletedExample 7 — Read a concrete strength report before judging the structure
A report shows one low concrete strength value. Determine the review sequence before concluding that the structural concrete is deficient.
Step-by-Step Solution
0 of 3 Steps CompletedExample 8 — Control the applicable DPWH/project document
A contractor cites a remembered “Blue Book item number” from an older project as proof that a material and test frequency are acceptable on a new DPWH contract. Determine the document-control response.